TM 5-3610-293-13&P
4-25. COMPLEXING KIT. The complexing kit provides a covered passageway from the Press Section Shelters to the
Finishing Section Shelter. Refer to TM 10-5411-203-13/23P for repair procedures on the complexing kit.
4-26. ISO SHELTER. The ISO shelter is a standard Army expandable shelter that houses the components of the Press
Section. Refer to TM 10-5411-200-14 for repair procedures on the ISO shelter.
4-27. PHASE MONITOR METER. Refer to figure 4-34 for location of components and hardware of the phase monitor
meter.
This task covers:
a.
Repair
INITIAL SETUP
Tools
Electrical Equipment Tool Kit
Materials
None
WARNING
The main power cable to the Press Section MUST be disconnected before
performing any maintenance on the phase monitor meter. Failure to do so may
result in DEATH or serious injury.
a.
Repair by replacing voltage meter.
(1) Remove phase monitor meter (1) from wall by removing screws (2), lockwashers (3) and flat washers (4).
(2) Tag and disconnect wires (5).
4-82