2-13. ASSEMBLY AND PREPARATION FOR USE.
a.
Site Selection. Refer to Figure 2-11 for a typical setup of the MPS system. The site selected should be as
follows:
(1)
Terrain slope can be no more than 8 inches over the 120 foot depth or width of the site.
(2)
Module B and C unexpanded shelters must be positioned no less than 232 inches apart and no more than
241 inches apart.
(3)
Module B and C expanded shelters must be no less than 66 inches apart and no more than 75 inches
apart.
(4)
Site should allow for a reasonable maneuvering area around the equipment.
(5)
Terrain should be firm, reasonably level, well drained and relatively free of large surface rocks.
NOTE
The solar bar levers on the rear end of the shelter have been removed due to lack of clearance at the air
conditioner housing. A ratchet wrench is supplied for use in rotating the solar bar and is stowed inside the
cargo door on the 36,000 BTUH air conditioner side.
b.
Setup of Shelter. Refer to TM 10-5411-200-14 for detailed instructions for setting up the shelter.