4-23. POWER DISTRIBUTION BOX ASSEMBLY. - Continued
g.
Repair by replacing Voltage Meter, Power Distribution Box Assembly. (See figure 4-25.)
(1)
Request generator operator shut down generator and disconnect main power cable (1).
(2)
Raise control panel cover (2) and request Module C supervisor place circuit breaker (3) in OFF
position.
(3)
Remove control panel assembly (4). (See a. above.)
(4)
Tag and disconnect terminal wires (5) from voltage meter (6).
(5)
Remove nuts (7), lockwashers (8), and voltage meter (6).
(6)
Position replacement voltage meter (6) and secure with lockwashers (8) and nuts (7).
(7)
Connect terminal wires (5) to voltage meter (6) and remove tags.
(8)
Secure control panel assembly (4) to power distribution box assembly (9). (See a. above.)
(9)
Request generator operator connect main power cable (1), and turn on generator. Test
operation, and request Module C supervisor place circuit breaker (3) in ON position.
Figure 4-25. Replacing Voltage Meter,
Power Distribution Box Assembly
4-55