TM 5-3610-295-13&P-2
2-8. ASSEMBLY AND PREPARATION FOR USE. - Continued
e. Checking Unpackaged Equipment. - Continued
(2) Check the equipment against the packing slip to see if the shipment is complete. Report all
discrepancies in accordance with the instructions of DA Pam 738-750.
f. Installation Instructions. The Press Shelter is installed for operation on the bed of a 2-1/2 ton cargo truck.
The individual items of equipment in the Press Shelter are usually transported intact in their operating position and no
installation procedures are deemed necessary.
g. Installing Boarding Ladder.
NOTE
This procedure is performed only if the shelter is to remain on the truck bed for operation.
(1)
Unbuckle ladder mounting strap (1).
(2)
Lift ladder (2) from mounting (3) on exterior wall.
(3)
Insert holding brackets (4) on edge of tailgate (5).
(4)
Attach hooks (6) of ladder stabilizers to underside lip of truck bed.
Figure 2-3. Installing Boarding Ladder
2-12