TM 5-3610-295-13&P-2
4-21. AIR CONDITIONER ASSEMBLY. - Continued
b.
Replace Air Conditioner. - Continued
(27)
Remove collar (6) from replacement air conditioner (1).
(28)
Remove screws (27) and air conditioner top cover (28).
(29)
Install blind rivet nuts (29) in the eight drilled holes.
(30)
Install air conditioner top cover (28) with screws (27).
(31)
Install collar (9, Figure 4-14) with bolts (6), lockwashers (7), and flatwashers (8).
(32) Apply a bead of RTV sealant (2, Appendix E) to front and rear inside of collar (9) where it meets the air
conditioner (10).
WARNING
Serious injury could result if heavy equipment is moved/lifted without sufficient personnel. Use a
suitable device/dolly if possible or have sufficient personnel available for the task to prevent injury
to personnel.
Sling must go through air conditioner handles to prevent air conditioner from falling and injuring
personnel.
(33)
Attach sling (1) to air conditioner (2) as shown in Figure 4-15. Attach sling (1) to forklift.
(34)
Coat the face of the collar (6, Figure 4-16) that mates with the outer frame (9) with RTV sealant
(2, Appendix E).
(35)
Raise air conditioner (1) and position into outer frame (9).
(36)
Secure air conditioner (1) to outer frame (9) with flat washers (5), lockwashers (4), and nuts (3)
and remove sling (1, Figure 4-15.)
4-46