TM 5-3610-295-13&P-1
SECTION III. OPERATION UNDER USUAL CONDITIONS
2-14.
ASSEMBLY AND PREPARATION FOR USE.
a.
Site Selection.
(1)
Select a site where ground is firm, dry and has good drainage.
(2)
Level ground on which truck containing the Editorial Shelter will be parked.
(3)
For site selection for the complete MPS, refer to TM 5-3610-294-13&P.
b.
Unloading Shelter.
(1)
Loosen tiedown turnbuckles and remove sling hooks from transporter and tiedown rings.
(2)
Remove any blocking between shelter and transporter.
(3)
Install sling assembly to lifting eyes and lifting hook.
(4)
Tie a 1/2 inch (13 mm) rope at least 15 feet (4.6 meters) long to each rear shelter towing eye.
(5)
Position a man on each rope to assist in positioning shelter during lifting operation.