TM 5-3610-295-13&P-2
1-14. TECHNICAL PRINCIPLES OF OPERATION. - Continued
b. MPS Finishing Section (Module C). Module C is comprised of one Finishing Section which is also a two-sided
ISO shelter equipped with a programmable electronic paper cutter, environmental controls, storage cabinets and work
tables. Two ISO-to-ISO connectors allows passage between the three ISO units.
c. Power Requirements and Distribution. Power for the entire system is provided by a 60 KW trailer-mounted
generator. Module A, when operated in a stand-alone configuration without Module B and C, has its own power source of
two 15 KW generators that are part of the standard Printing Plant, Special Warfare, Transportable configuration. When
Module A is configured with Modules B and C, the two 15 KW generators are replaced by the single 60 KW power plant
providing power for the entire system. A Power Distribution Box Assembly provides central power distribution and control
to the five units of the MPS.
d. Movement of the Printing Plant. Movement of the Printing Plant, Special Warfare Transportable is
accomplished by two 2 1/2 ton cargo trucks.
Figure 1-5. The Printing Process
1-14